The pictures on this page are in chronological order. The most recent pictures are located at the top of this page. The oldest pictures are located at the bottom of this page.
The pictures below were taken on or after November 16, 2009. External electric work is completed (electric connection made Nov 24). Porches take shape. Fascia is installed. Sidewalks are poured; pervious concrete is poured in parking lot (Nov 23). Macadam is laid Dec 2. Parking lot lights are installed Jan 16. Dryvit (stucco) is started Jan 20. Final landscaping started April 1.